Road · Building · Drain · Culvert | Designed by Vinayak Vasudev Naik · Version 1 · Integrated Karnataka PWD SOR 2021–22
Enter the project details, choose work types and record item-wise component measurements. The complete uploaded SOR catalogue is built into this file.
Select Road, Building, Drain and/or Culvert above. Every selected work type shows all its components. Sl. No. is assigned in measurement-entry order across selected work types. Add a Custom Component from the work-type header. Quantities include Numbers × dimensional or direct quantity.
Automatically reads the calculated m³ quantities of RCC items from selected Road, Building, Drain and Culvert components. Enter an editable steel percentage for each RCC measurement. This is a preliminary steel allowance, not a bar-bending schedule or an additional SOR measurement.
| Entry Sl. | RCC? | Work type | Component | SOR item / RCC specification | RCC Qty (m³) | Steel % (editable) | Steel (kg) | Steel (MT) | Rate (₹/kg) | Steel amount (₹) |
|---|
RCC detection uses the SOR specification and the assigned component. Plain cement concrete, formwork and separately entered reinforcement are not automatically included. Use “Show all m³ rows” to include or exclude any ambiguous RCC item. Steel allowance is reported separately to avoid double-counting with SOR steel items.
Quantity is calculated automatically from the SOR unit: m³ = Numbers × L × B × H; m² = Numbers × L × B; Rmt = Numbers × L; kg/MT/Nos = Numbers × direct quantity. Inapplicable dimension cells are locked.
| Sl. No. | SOR item no. / Search | Component | Specification / description | Numbers | Length | Breadth | Height / Depth | Quantity (auto) | Unit | Rate / unit (₹) | Amount (₹) | Remarks |
|---|
Some item numbers repeat in the supplied workbook. Confirm the specification, unit, rate and Excel row when selecting.